Montgomery Upper Middle School Kitchen Piping Replacement Project
Completed: June-August 2016
Scope of Work: This summer project was to replace all of the sanitary waste piping under the kitchen floor of a middle school. We x-rayed and saw cut the concrete floor, excavated trenches, replaced approximately 200’ of cast iron piping in the ground with new cast iron pipe, replaced numerous electrical lines in the concrete floor, poured a new concrete floor, installed new tile and re-installed the kitchen equipment.
St. Peter’s Church Boiler Replacement
Completed: October 2014
Scope of Work: This unique project involved converting a 160 year old church from steam to hot water heat. We removed the existing steam boiler, piping and radiators, and installed all new hot water piping throughout the church and offices, along with new fin-tube convectors and fan coils, and a new 1.2 million BTU boiler. This project also involved building custom millwork enclosures and modifying approximately 50 existing pews to accommodate the new heating units.
YMCA New Mechanical Equipment
Completed: During one week in August 2016
Scope of Work: This one of a kind project involved replacing the mechanical plant for a busy YMCA during a one week shut down. We installed new gas piping, two new water heaters, two new storage tanks, three new pool heaters, a new circulator, and associated water piping and stainless steel vent piping, along with a new water booster pump and storage tank.
Aurolife – 100,000 Square Foot Addition to Pharmaceutical Plant
Completed: January 2018
Scope of Work: Our scope of work on this project is to install the new underground sanitary, storm and process waste piping, along with the roof drains and storm drain risers for a new pharmaceutical plant. We are excavating, installing new PVC pipe in various sizes up to 12”, backfilling and compacting, and installing new risers to the 50’ high roof with 15 new roof and overflow drains.
New Bottle Filling Station Installations at Various Schools
Completed: At approximately 20 different schools, we have installed over 60 new bottle filling stations in the past four years
Scope of Work: We have installed numerous different bottle filling stations. Many of the installations involve opening masonry walls to relocate piping, framing the opening, closing the wall and installing decorative paneling to cover the wall. We then mount the new bottle filling station on the paneling for a clean finished look.
New Water Heaters at Elementary School
Completed: August 2016
Scope of Work: We removed an existing commercial water heater and 1000 gallon storage tank from the mechanical room at an elementary school, and installed two new gas-fired A.O. Smith high efficiency commercial water heaters. This improvement project has saved the school money on their gas and electric bills, along with cleaning up the mechanical room, and giving them more space.
Trenchless Sewer Replacement at Elementary School
Completed: September 2021
Scope of Work: This rush project was an emergency replacement of a 325-foot sewer line with a new tap on the city main right before school started. We pipe burst a 90-foot section under the parking lot behind the school, and burst a 180-foot section down the driveway, increasing the pipe from a 4” pipe to a 6” pipe in the process. We excavated and replaced an approximately 65’ section where other lines from the building tied in. We also installed a new tap on the 12’ deep city main line, and restored the concrete, asphalt and grass.